The City of Dallas is looking to find a solution to the controversial Jefferson Boulevard Viaduct connection, presenting an alternative route at recent community meetings, including one in West Dallas on Thursday.

The new proposed route would connect the viaduct to downtown by going underneath the Kay Bailey Hutchison Convention Center and connecting with Lamar Street.

Earlier this year, Dallas City Council members and residents were critical of plans altering the current Oak Cliff to downtown connection through the Jefferson viaduct.

Those plans would have ended the viaduct at the intersection of Hotel Street and Memorial Drive to accommodate for the convention center’s $3.5 billion expansion.

The issue could have been resolved by lifting the convention center above Jefferson — which was a part of the original plan — but city council voted against this due to its $500 million cost.

Now, city staff are proposing an alternative option.

The Jefferson viaduct would downramp into the Hotel Street and Memorial Drive intersection, but then continue onto Memorial Drive underneath the convention center and connect with Lamar Street.

The northbound section of the viaduct north of the central parking garage would be downgraded to two lanes. Additionally, a far-right lane would connect to Hotel Street to the east and a far-left lane would become southbound from Lamar Street to the parking garage.

The southbound Houston Street Viaduct, which runs parallel to Jefferson, would remain unchanged.

However, this plan would accommodate any future conversion of Houston to a pedestrian green space and public transit route. This conversion has not yet received any approval or funding.

Attendees at the Thursday community meeting had concerns about this plan, in particular the traffic during the construction period.

While the project would be constructed, Jefferson would end near the parking garage, and connect into the Houston viaduct, which would be converted to a two-way street.

City staff did not have a graphic depicting this traffic flow. Staff said construction would be completed in the first quarter of 2031.

West Dallas residents were worried about how this traffic congestion may increase traffic at the Margaret Hunt Hill and West Commerce Street bridges.

Staff said this plan was in the early stages of development, with further stakeholder feedback opportunities in the future.

Share This Story, Choose Your Platform!